Construction moving forward on Zilwaukee Bridge in Michigan

The Zilwaukee Bridge is still undergoing repairs. (Michigan Department of Transportation)

The Associated Press

5/5/2008

ZILWAUKEE, Mich. — State transportation officials say work is progressing on Interstate 75 across the Zilwaukee Bridge.

WSGW-AM and WNEM-TV report drivers will soon see a brace on the outside of the bridge's northbound lanes.

Engineers designed the brace after workers unexpectedly nicked several reinforcing steel inside the concrete span last month.

The $3.3 million project hit a snag when crews determined that more than 30 new bearings weren't designed properly. Each circular bearing weighs a few thousand pounds, and is 3 feet in diameter.

The bearings allow the bridge to expand and contract with temperature variations.

Those traveling northbound on I-75 are advised to use I-675 as an alternate route.

 