The Indiana Department of Transportation is providing a progress update on the North Split reconstruction project one year after the interchange’s full closure.  

INDIANAPOLIS – The Indiana Department of Transportation is providing a progress update on the North Split reconstruction project one year after the interchange’s full closure.

Since May 15, 2021, North Split construction crews have:

  • Successfully demolished 38 of 51 bridges in need of repair;
  • Placed 217 of 390 precast concrete beams, with the largest weighing approximately 250,000 pounds;
  • Reconstructed 4 bridges and 1 ramp, which are currently in use;
  • Used approximately 34,000 cubic yards of structural concrete; and
  • Moved over 560,000 cubic yards of the 1 million total cubic yards of earthwork.

The North Split is the busiest interchange in central Indiana.

After 50 years of service, the North Split’s deteriorating condition made reconstruction necessary to rehabilitate and improve the existing interstate facilities.  A more efficient and compact redesign of the interchange eliminates merging and weaving conditions that contribute to high crash rates and congestion.

The interchange is scheduled to reopen by the end of 2022 with landscaping, aesthetics and local street work continuing into spring 2023. The North Split landscaping design will include the use of native, low-maintenance plants to soften urban elements and provide a diverse palette of plant species, including native grasses, small shrubs, large deciduous shrubs, ornamental trees, and shade trees.

The project will also result in improved lighting, visibility and pedestrian safety at bridge underpasses. Once North Split reconstruction is complete, project area improvements will include:

  • 223 new lighting elements, including 12 high-mast tower lights, 176 underpass and monument lights at bridges, and 33 conventional roadway light structures;
  • Approximately 12,100 linear feet of new sidewalks/trails;
  • More than 4,500 trees; and
  • More than 5,000 shrubs.

For up-to-date project information, visit northsplit.com or text “NORTHSPLIT” to 468311. Follow the North Split project’s progress on social media at:

Facebook: Facebook.com/NorthSplit

Twitter: @NorthSplit

Instagram: @IndyNorthSplit

 

The Trucker News Staff

The Trucker News Staff produces engaging content for not only TheTrucker.com, but also The Trucker Newspaper, which has been serving the trucking industry for more than 30 years. With a focus on drivers, the Trucker News Staff aims to provide relevant, objective content pertaining to the trucking segment of the transportation industry. The Trucker News Staff is based in Little Rock, Arkansas.

Avatar for The Trucker News Staff
The Trucker News Staff produces engaging content for not only TheTrucker.com, but also The Trucker Newspaper, which has been serving the trucking industry for more than 30 years. With a focus on drivers, the Trucker News Staff aims to provide relevant, objective content pertaining to the trucking segment of the transportation industry. The Trucker News Staff is based in Little Rock, Arkansas.
For over 30 years, the objective of The Trucker editorial team has been to produce content focused on truck drivers that is relevant, objective and engaging. After reading this article, feel free to leave a comment about this article or the topics covered in this article for the author or the other readers to enjoy. Let them know what you think! We always enjoy hearing from our readers.

COMMENT ON THIS ARTICLE